Vectura Pharmaceuticals

Kerr Office Group Vectura Clean Room
  • Connector.

    Location

    Chippenham WILTS

  • Connector.

    Value

    £1,200,000

  • Connector.

    Start Date

    JUNE 2008

  • Connector.

    Completion Date

    OCTOBER 2008

Kerr Office Group Clean Room Construction

Scope of Works

In conjunction with a Clean Room design specialist, develop and build a manufacturing facility within an existing warehouse including the installation of an electrical substation and associated drainage.
The whole facility was designed to save on running costs and therefore uses re-circulated air. This air passes through a bank of safe change HEPA filters before it passed back to the air handling unita for re-use.

Challenges Resolved

Designing a mezzanine floor with load bearing capabilities for the manufacturing plant.
Creating a layout following and in keeping with the clients brief and requirements. Consulting with Building Control.